Last date & time for issuance of ITB: | 2nd November 2023 till 05:00 p.m. |
Last date & time for Tender submission: | 3rd November 2023, from 09:00 to 05:00 p.m. |
Tender Opening date and time: | 13th November 2023 at 03:00 p.m. |
Tender Fee: | Nil |
Strengthening Participatory Organization invites sealed bids from qualified Vendors / Contractors and Construction firms duly registered with the Government of the Islamic Republic of Pakistan having a valid 2022-23 Pakistan Engineering Council (PEC) Certificate to submit a firm offer for the Construction of different components of Spate Irrigation PROJECT at Tehsil Bhag, District Kachi, Balochistan. The offers from the successful bidders would form the basis for an award of a contract.
The following annexes form are and shall be an essential part of this Bid:
Annex A: Price Proposal / Bill of Quantities for the Construction of different spate irrigation systems and canals in the project area.
Annex B: Technical Proposal Form
Annex C: Vendor’s General Information.
Bidders are requested to confirm the receipt of this ITB and send the expression of their intention to participate to the addresses (physical) provided in the “SUBMISSION OF BIDS” section of this ITB.
IMPORTANT: Any direct correspondence of your offer with the responsible buyer will disqualify the proposal. Please bring your proposal directly to the address provided in the “SUBMISSION OF BIDS” section of this ITB.
YOUR OFFER:
Please submit your offer using the submission templates provided (Annex –A). It should conform to the following requirements and contain all information required. The bids that do not conform to the requested format will not be considered for evaluation. Your Bid should include the following information:
IMPORTANT: Firms are required to quote rates (for each job/work) without skipping any job/work in Annex A. Incomplete or partial bids will not be entertained and will be considered non-responsive and will be rejected. Escalation of rates or withdrawal/ surrender in the submitted bid form is not allowed.
WORKING TIME: All the mentioned work must be completed as per the specifications/ instructions on the specified locations within six months or AS EARLIER AS POSSIBLE after placement of the Work Order.
And those applicable from the following documents
The qualified vendors will be added to the Tender Analysis Report after investigation of suitability based on the submitted Vendor’s general information form and supporting documents. The investigation involves consideration of several factors such as:
This will be followed later by performance evaluation as a contractor such as:
All bids from vendors will be evaluated based on:
IMPORTANT: The offers submitted must be in Pakistani Rupees.
Bids must be submitted in two (02) separately sealed envelopes as follows:
The outer envelope should be marked and addressed as mentioned below.
(One) sealed envelope containing technical part of the offer having the following documents:
1.1. Duly filled Vendor General Information Form
2.1. Duly filled Bid Proposal Form
Both envelopes A and B should be sealed and put in envelope C, having written the below-mentioned details as illustrated above. The envelopes should be brought by the representative of the firm/company on the closing date and time as mentioned above.
Chairperson
SPO Procurement Committee
SPO National Centre
Building No. 1-B, St. No. 26, Sector G-9/1, ISLAMABAD.
Phone: 051- 8736193-4
IMPORTANT: Bids that are otherwise addressed and/or copied or sent to other addresses or individuals will be marked invalid and will not be considered for evaluation.
All bids must be received latest by COB on Friday, 3rd November 2023.
LATE SUBMISSION OF BIDS: Bids received after the deadline for submission of bids and bids transmitted in any other manner than those indicated above will not be considered.
The offers must bear your official letterhead, clearly identifying your Company.
Bid Opening: A sealed envelope containing the commercial part of the offer will only be opened for evaluation if the supplier’s technical part of the offer has passed the technical Evaluation / has been accepted by SPO Technical Procurement Committee as meeting the technical specifications. The Bids will be opened in front of the procurement Committee of SPO in the presence of Committee Members at 03:00 p.m. on 13th November 2023.
SPO reserves the right to accept the whole or part of your Bid. Please note (The lowest offer is not the only criteria for acceptance of the offer) refer to the stated evaluation criteria (Para C above). Information provided by the bidder will constitute the basis for the eventual award of the contract.
SPO may, at its discretion, extend the deadline for the submission of proposals by notifying all prospective vendors in writing. The extension of the deadline may accompany a modification of the solicitation documents prepared by SPO on its initiative or in response to a clarification requested by a prospective supplier.
Any Work Order (W.O.) issued as a result of this ITB will be made in Pakistani Rupees (PKR), payment will be in accordance with the deliverables / work done. Final payment will be made within fifteen (15) working days after completion of construction work and submission of Work Completion Report as per BoQs duly signed by the Project nominated person. Applicable Government tax(s) at an admissible rate(s)shall be deducted at source from the payment made to the selected Vendor.
In case of any dispute or disagreement between SPO and the Vendor, the dispute shall be referred to adjudication or arbitration in accordance with the laws of the Islamic Republic of Pakistan, and the venue for the arbitration will be Quetta.
Yours sincerely,
Chairperson
SPO Procurement Committee
__________________________________________________________________________________________
PRICE PROPOSAL SHEET / BOQ
Description and Specifications
Technical Proposal Form
Particulars |
Description | Attachments
(Annexure Nos.) |
Name of the Firm: | ||
Address:
Telephone, Fax & E-mail |
||
Year of Establishment
(attach any documentary evidence or furnish a statement on Oath) |
||
VALID Pakistan Engineering Council Registration No. and Certificate
(Attach updated PEC certificate) |
||
Income Tax registration certificate
(Attach Active certificate) and BRA registration. |
||
Tender fee
|
N/A | N/A |
Earnest Money (5% of the total bid value) in the shape of Pay order or demand draft in favour of SPO | Yes
No |
|
Banker’s name and Contact details | ||
Experience related to Similar Work. (Completed projects). Please indicate name of client and value of service agreement in a separate annex. Attach P.O/service agreements (if any) | ||
Assignment/ projects in hand.
Please indicate name of client and value of service agreement in a separate annex. Attach service agreement (if any) |
||
Annual turnover supported by sales income tax return for the year 2019, 2020 and 2021 | ||
Affidavit: (that the firm has not been blacklisted by private, Govt. Semi Govt. and Autonomous Body) | ||
Type and No. of Machinery / Equipment | ||
Contact Person:
Date:______________________ |
Name & Designation
Authorized Signature & Stamp |